IP-625
200 MW hybrid in Jerome, ID · In queue since October 2021 · Proposed COD December 2025
200 MW
Capacity
1
Components
Solar
4y 7m
In Queue
IA Executed
IA Status
Signed Sep 2023
Queue → IA
1y 11m
IA → COD
2y 3m
Total Duration
1y 11m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Construction pending
Typical: 18–30 months
Proposed COD: 2025-12-01
IP-625 is a proposed 200 MW solar and battery hybrid project located in Jerome County, Idaho. The project, being developed by Invenergy Solar Project Development LLC, consists of 200 MW of solar generation. It is interconnected to the Idaho Power Company grid at the Midpoint 230kV Switchyard.
The project entered the Idaho Power (IP) interconnection queue on October 26, 2021, with a proposed commercial operation date of December 1, 2025. The interconnection agreement for IP-625 was executed on September 18, 2023. The project's current interconnection status is listed as suspended.
Generated from interconnection queue and public data sources
State
ID
County
Jerome
Grid Region
Mountain West
Market
—
Developer
Invenergy Solar Project Development LLC
Utility
Idaho Power Company
Entity
IP
Service Type
—
Point of Interconnection
Midpoint 230kV Switchyard
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN