IP-630
53 MW hybrid in Elko, NV · In queue since January 2022 · Proposed COD January 2025
53 MW
Capacity
1
Components
Solar
4y 4m
In Queue
IA Executed
IA Status
Signed Apr 2023
Queue → IA
1y 3m
IA → COD
1y 9m
Total Duration
1y 3m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Construction pending
Typical: 18–30 months
Proposed COD: 2025-01-01
IP-630 is a proposed 53 MW hybrid solar and battery project located in Elko County, Nevada. The developer is Elko County Solar 1, LLC, and the project is interconnected with Idaho Power Company. The proposed project consists of 53 MW of solar capacity.
The project is listed in the Idaho Power (IP) interconnection queue as of January 10, 2022, with a proposed commercial operation date of January 1, 2025. The interconnection agreement (IA) was executed on April 24, 2023, and the project's current status is listed as suspended. The point of interconnection (POI) is the Upper Salmon_x0013_Wells 138kV Line.
Generated from interconnection queue and public data sources
State
NV
County
Elko
Grid Region
Mountain West
Market
—
Developer
Elko County Solar 1, LLC
Utility
Idaho Power Company
Entity
IP
Service Type
—
Point of Interconnection
Upper Salmon_x0013_Wells 138kV Line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project IP-630