IP-635
1,000 MW hybrid in Gooding, ID · In queue since February 2022 · Proposed COD December 2026
1,000 MW
Capacity
1
Components
Solar
4y 3m
In Queue
IA Executed
IA Status
Signed Jun 2023
Queue → IA
1y 4m
IA → COD
3y 6m
Total Duration
1y 4m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Construction pending
Typical: 18–30 months
Proposed COD: 2026-12-01
IP-635 is a proposed 1000 MW hybrid solar and battery project located in Gooding County, Idaho. The development project, which also lists wind as a technology detail, is being developed by Taurus Wind LLC and is interconnected with Idaho Power Company. The point of interconnection is the Midpoint 500kV Substation.
The project entered the IP (Idaho Power) interconnection queue on February 7, 2022, with a proposed commercial operation date of December 1, 2026. The interconnection agreement for IP-635 was executed on June 13, 2023, and the project's current status is listed as suspended. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
ID
County
Gooding
Grid Region
Mountain West
Market
—
Developer
Taurus Wind LLC
Utility
Idaho Power Company
Entity
IP
Service Type
—
Point of Interconnection
Midpoint 500kV Substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.