IP-654
130 MW hybrid in Bingham, ID · In queue since May 2022 · Proposed COD December 2025
130 MW
Capacity
1
Components
Solar
4 years
In Queue
IA Executed
IA Status
Signed Nov 2023
Queue → IA
1y 6m
IA → COD
2y 1m
Total Duration
1y 6m
Schedule
4 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2025-12-31
IP-654 is a proposed 130 MW hybrid solar and battery project located in Bingham County, Idaho. The project, developed by Pingree Solar LLC, consists of 130 MW of solar capacity. It is interconnected to the Idaho Power Company grid at the Pingree 138kV Substation.
The project is listed in the IP (Idaho Power Company) interconnection queue as of May 3, 2022, with a proposed commercial operation date of December 31, 2025. The interconnection agreement for the project was executed on November 2, 2023.
Generated from interconnection queue and public data sources
State
ID
County
Bingham
Grid Region
Mountain West
Market
—
Developer
Pingree Solar LLC
Utility
Idaho Power Company
Entity
IP
Service Type
—
Point of Interconnection
Pingree 138kV Substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.