Project IP-655 — Project Summary

Queue ID
IP-655
Capacity
325 MW
Technology
Solar+Battery
Status
active
Location
Bear Lake, ID
Region
West
Developer
Aurora Solar LLC
IA Status
IA Executed

IP-655

IP-655BetaActiveSolarBatteryIPLBNL

325 MW hybrid in Bear Lake, ID · In queue since May 2022 · Proposed COD December 2025

325 MW

Capacity

1

Components

Solar

4 years

In Queue

IA Executed

IA Status

Signed Dec 2023

Interconnection

Queue → IA

1y 7m

IA → COD

2 years

Total Duration

1y 7m

Schedule

4 months past proposed COD

Construction75%
Queue EntryMay 10, 2022

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection AgreementDec 14, 2023

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 18–30 months

Commercial Operation

Proposed COD: 2025-12-31

About

The proposed IP-655 project is a 325 MW solar and battery hybrid development located in Bear Lake County, Idaho. Being developed by Aurora Solar LLC, the project consists of 325 MW of solar capacity. It is interconnected to the Idaho Power Company grid at the Bridger_x0013_Populus 345kV Line.

The project is listed in the IP (Idaho Power) interconnection queue with an entry date of May 10, 2022, and a proposed commercial operation date of December 31, 2025. An Interconnection Agreement (IA) for the project was executed on December 14, 2023. The project's interconnection status is listed as active.

Generated from interconnection queue and public data sources

Project Details

State

ID

County

Bear Lake

Grid Region

Mountain West

Market

Developer

Aurora Solar LLC

Utility

Idaho Power Company

Entity

IP

Service Type

Point of Interconnection

Bridger_x0013_Populus 345kV Line

Data Source

LBNL

Market Context
Approximate
ISO / RTO
MOUNTAIN_WEST
Trading Hub
MID-C
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.