IP-665
400 MW hybrid in Ada, ID · In queue since August 2022 · Proposed COD December 2027
400 MW
Capacity
1
Components
Solar
3y 9m
In Queue
IA Executed
IA Status
Signed Apr 2024
Queue → IA
1y 8m
IA → COD
3y 8m
Total Duration
1y 8m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2027-12-31
IP-665 is a proposed 400 MW solar and battery hybrid project located in Ada County, Idaho. The development project, under the name Blacks Creek Energy Center, LLC, is interconnected with Idaho Power Company (IP). The project consists of 400 MW of solar capacity.
The project is listed as active in the IP interconnection queue, with an entry date of August 16, 2022, and a proposed commercial operation date of December 31, 2027. The interconnection agreement (IA) was executed on April 4, 2024. The point of interconnection is the BOBN_x0013_Hubbard 230kV Line.
Generated from interconnection queue and public data sources
State
ID
County
Ada
Grid Region
Mountain West
Market
—
Developer
Blacks Creek Energy Center, LLC
Utility
Idaho Power Company
Entity
IP
Service Type
—
Point of Interconnection
BOBN_x0013_Hubbard 230kV Line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project IP-665