IP-669
200 MW hybrid in Ada, ID · In queue since August 2022 · Proposed COD December 2025
200 MW
Capacity
1
Components
Solar
3y 9m
In Queue
IA Executed
IA Status
Signed Nov 2023
Queue → IA
1y 3m
IA → COD
2y 1m
Total Duration
1y 3m
Schedule
4 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2025-12-31
IP-669 is a proposed 200 MW hybrid solar and battery project located in Ada County, Idaho. The project, developed by Bluebird Solar Project, LLC, consists of 200 MW of solar generation. It is interconnected to the Idaho Power Company system at the BOBN_x0013_Hubbard 230kV Line.
The project is listed in the IP interconnection queue with an entry date of August 29, 2022, and a proposed commercial operation date of December 31, 2025. An Interconnection Agreement (IA) for the project was executed on November 9, 2023.
Generated from interconnection queue and public data sources
State
ID
County
Ada
Grid Region
Mountain West
Market
—
Developer
Bluebird Solar Project, LLC
Utility
Idaho Power Company
Entity
IP
Service Type
—
Point of Interconnection
BOBN_x0013_Hubbard 230kV Line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.