330 MW storage in Owyhee, ID · In queue since December 2022 · Proposed COD June 2026
330 MW
Capacity
1
Components
Battery
3y 5m
In Queue
IA Executed
IA Status
Signed Jan 2024
Queue → IA
1y 1m
IA → COD
2y 5m
Total Duration
1y 1m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2026-06-01
IP-696 is a proposed 330 MW battery storage project located in Owyhee County, Idaho. Developed by KCE ID 1, LLC, the project is interconnected to Idaho Power Company via the Hemingway 230kV Substation.
The project is listed in the IP (Idaho Power) interconnection queue with a queue entry date of December 28, 2022. The proposed commercial operation date is June 1, 2026, and an Interconnection Agreement (IA) was executed on January 29, 2024.
Generated from interconnection queue and public data sources
State
ID
County
Owyhee
Grid Region
Mountain West
Market
—
Developer
KCE ID 1, LLC
Utility
Idaho Power Company
Entity
IP
Service Type
—
Point of Interconnection
Hemingway 230kV Substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.