100 MW storage in Canyon, ID · In queue since June 2023 · Proposed COD December 2027
100 MW
Capacity
1
Components
Battery
2y 11m
In Queue
IA Executed
IA Status
Signed Dec 1999
IA → COD
28 years
Total Duration
2y 11m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2027-12-31
IP-723 is a proposed 100 MW battery storage project located in Canyon County, Idaho. The project is in the Idaho Power Company interconnection queue (IP) with a queue entry date of June 9, 2023, and a proposed commercial operation date of December 31, 2027. The interconnection agreement for the project has been executed, though the execution date of December 31, 1999, appears to be a placeholder. The point of interconnection is the Bowmont 230kV Substation.
The development project consists solely of battery storage, with a total capacity of 100 MW. It is currently listed as an active project in the interconnection queue.
Generated from interconnection queue and public data sources
State
ID
County
Canyon
Grid Region
Mountain West
Market
—
Developer
—
Utility
Idaho Power Company
Entity
IP
Service Type
—
Point of Interconnection
Bowmont 230kV Substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project IP-723