IP-747
1.5 MW generation in Twin Falls, ID · In queue since May 2024 · Proposed COD March 2025
1.5 MW
Capacity
1
Components
Hydro
2 years
In Queue
IA Executed
IA Status
Signed Dec 1999
IA → COD
25y 3m
Total Duration
2 years
Schedule
14 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–36 months
Proposed COD: 2025-03-05
IP-747 is a proposed 1.5 MW hydroelectric generation project located in Twin Falls County, Idaho. The project, which is interconnected with Idaho Power Company, entered the IP interconnection queue on May 23, 2024, with a proposed commercial operation date of March 5, 2025.
The project's interconnection agreement (IA) has been executed, with an IA date of December 31, 1999. The point of interconnection (POI) is the Distribution Feeder.
Generated from interconnection queue and public data sources
State
ID
County
Twin Falls
Grid Region
Mountain West
Market
—
Developer
—
Utility
Idaho Power Company
Entity
IP
Service Type
—
Point of Interconnection
Distribution Feeder
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.