Emery Meadow Solar
16.425 MW generation in York, ME · In queue since April 2020 · Proposed COD September 2026
16.425 MW
Capacity
1
Components
Solar
6y 1m
In Queue
IA Executed
IA Status
COD target: 2026
Total Duration
6y 5m
Interconnection request submitted to ISO/RTO
ISO-NE is transitioning to cluster studies per FERC Order 2023.
Typical: 25–30 months (recent)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2026-09-30
The Emery Meadow Solar project is a proposed 16.42 MW solar generation facility in York County, Maine. The project, developed under the ISO-NE queue as queue ID ISO-NE-1021, entered the interconnection queue on April 27, 2020, and has a proposed commercial operation date of September 30, 2026. The interconnection agreement for the project has been executed.
The proposed project is linked to the existing Emery Meadow Solar Station (EIA plant ID 65366). The point of interconnection is CMP 34.5 kV, Section 182. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
ME
County
York
Grid Region
ISO New England
Market
ISO/RTO Member
Developer
—
Utility
ISO-NE
Entity
ISO-NE
Service Type
—
Point of Interconnection
CMP 34.5 kV, Section 182
Data Source
LBNL + Live
- ISO / RTO
- ISO-NE
- Trading Hub
- .Z.MAINE
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- LD.W_BUXTON34.5
- POI Substation
- Buxton Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Emery Meadow Solar