Husky Solar
50.159 MW generation in Windham, CT · In queue since June 2021 · Proposed COD May 2028
50.159 MW
Capacity
1
Components
Solar
4y 11m
In Queue
IA Executed
IA Status
COD target: 2028
Total Duration
6y 11m
Interconnection request submitted to ISO/RTO
ISO-NE is transitioning to cluster studies per FERC Order 2023.
Typical: 25–30 months (recent)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2028-05-10
Husky Solar is a proposed 50.16 MW solar generation project located in Windham County, Connecticut. The project is listed in the ISO-NE interconnection queue as queue ID ISO-NE-1138, with an interconnection queue entry date of June 3, 2021, and a proposed commercial operation date of May 10, 2028. The interconnection agreement for the project has been executed.
The point of interconnection will be located approximately 6.9 miles from the 1607/1505 line ROW (Exeter Tap) and about 1.1 miles from the Exeter Sub 54N along the 115 kV underground line to the Exeter Sub 54N. The development project has been mentioned in recent news coverage.
Generated from interconnection queue and public data sources
State
CT
County
Windham
Grid Region
ISO New England
Market
ISO/RTO Member
Developer
—
Utility
ISO-NE
Entity
ISO-NE
Service Type
—
Point of Interconnection
The POI will be located about 6.9 miles from the 1607/1505 line ROW (Exeter Tap) and about 1.1 miles from the Exeter Sub 54N along the 115 kV underground line to the Exeter Sub 54N.
Data Source
LBNL + Live
- ISO / RTO
- ISO-NE
- Trading Hub
- .Z.CONNECTICUT
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Husky Solar