Solar
20 MW generation in Rensselaer, NY · In queue since July 2021 · Proposed COD December 2022
20 MW
Capacity
1
Components
Solar
4y 10m
In Queue
—
IA Status
COD target: 2022
Total Duration
1y 5m
Schedule
41 months past proposed COD
Interconnection request submitted to ISO/RTO
ISO-NE is transitioning to cluster studies per FERC Order 2023.
Typical: 25–30 months (recent)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2022-12-30
The proposed Solar project, identified as ISO-NE-1147 in the ISO-NE interconnection queue, is a 20 MW solar generation facility planned for Rensselaer County, New York. The project entered the queue on July 8, 2021, with a proposed commercial operation date of December 30, 2022.
The interconnection point is specified as National Grid's North Troy – Hoosick 115kV Line #5. The project's status is currently listed as active, but no Interconnection Agreement (IA) status is specified in the data. The developer is not specified in the data, but the project has appeared in recent news.
Generated from interconnection queue and public data sources
State
NY
County
Rensselaer
Grid Region
ISO New England
Market
ISO/RTO Member
Developer
—
Utility
—
Entity
ISO-NE
Service Type
—
Point of Interconnection
National Grid_x0019_s North Troy _x0013_ Hoosick 115kV Line #5
Data Source
LBNL + Live
- ISO / RTO
- ISO-NE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Solar