Solar Knox
33.5 MW generation in Knox, ME · In queue since October 2021 · Proposed COD March 2027
33.5 MW
Capacity
1
Components
Solar
4y 7m
In Queue
IA Executed
IA Status
COD target: 2027
Total Duration
5y 5m
Interconnection request submitted to ISO/RTO
ISO-NE is transitioning to cluster studies per FERC Order 2023.
Typical: 25–30 months (recent)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2027-03-31
Solar Knox is a proposed 33.5 MW solar generation project located in Knox County, Maine. The project is listed in the ISO-NE interconnection queue as queue ID ISO-NE-1190, with an entry date of October 28, 2021. The proposed commercial operation date is March 31, 2027, and the interconnection agreement has been executed.
The project is interconnected to the CMP 115kV Line 80.
Generated from interconnection queue and public data sources
State
ME
County
Knox
Grid Region
ISO New England
Market
ISO/RTO Member
Developer
—
Utility
ISO-NE
Entity
ISO-NE
Service Type
—
Point of Interconnection
CMP 115kV Line 80
Data Source
LBNL + Live
- ISO / RTO
- ISO-NE
- Trading Hub
- .Z.MAINE
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Solar Knox