Solar
150 MW generation in Hartford, CT · In queue since March 2022 · Proposed COD November 2028
150 MW
Capacity
1
Components
Solar
4y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2028
Total Duration
6y 8m
Interconnection request submitted to ISO/RTO
ISO-NE is transitioning to cluster studies per FERC Order 2023.
Typical: 25–30 months (recent)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-11-01
The Solar project, identified as ISO-NE-1245 in the ISO-NE interconnection queue, is a proposed 150 MW solar generation facility in Hartford County, Connecticut. The project, consisting of 150 MW of solar capacity, entered the queue on March 31, 2022, with a proposed commercial operation date of November 1, 2028. Its interconnection agreement status is listed as "In Progress (unknown study)".
The proposed project's point of interconnection (POI) is the 345kV Line 3419 Tap between Meekville Junction/Barbour Hill (PSSE Bus Number: 119103) to Ludlow (PSSE Bus Number: 116045). The project has been mentioned in recent news coverage related to industry and regulatory matters.
Generated from interconnection queue and public data sources
State
CT
County
Hartford
Grid Region
ISO New England
Market
ISO/RTO Member
Developer
—
Utility
—
Entity
ISO-NE
Service Type
—
Point of Interconnection
345kV Line 3419 Tap between Meekville Junction/Barbour Hill (PSSE Bus Number: 119103) To LudlowPSSE Bus Number: 116045)
Data Source
LBNL + Live
- ISO / RTO
- ISO-NE
- Trading Hub
- .Z.CONNECTICUT
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26