Solar
25 MW generation in Hartford, CT · In queue since April 2022 · Proposed COD November 2025
25 MW
Capacity
1
Components
Solar
4y 1m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
3y 7m
Schedule
6 months past proposed COD
Interconnection request submitted to ISO/RTO
ISO-NE is transitioning to cluster studies per FERC Order 2023.
Typical: 25–30 months (recent)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-11-01
A proposed 25 MW solar project, known as "Solar" and identified as ISO-NE-1247, is under development in Hartford County, Connecticut. The project is located within the ISO-NE service region and entered the ISO-NE interconnection queue on April 5, 2022. Its proposed commercial operation date is November 1, 2025.
The interconnection agreement for the project is currently listed as "In Progress (unknown study)". The point of interconnection is planned at the Gravel Pit Solar QP 1030, via a Shared Facility. Specifically, it will involve a line cut and three-breaker ring bus of the 115 kV Connecticut Light & Power Company line between Barbour Hill and Windsor Locks.
Generated from interconnection queue and public data sources
State
CT
County
Hartford
Grid Region
ISO New England
Market
ISO/RTO Member
Developer
—
Utility
ISO-NE
Entity
ISO-NE
Service Type
—
Point of Interconnection
To interconnect at the POI of Gravel Pit Solar QP 1030, via a Shared Facility, QP 1030 is described as a line cut and three-breaker ring bus of the 115 kV Connecticut Light & Power Company line between Barbour Hill and Windsor Locks.
Data Source
LBNL + Live
- ISO / RTO
- ISO-NE
- Trading Hub
- .Z.CONNECTICUT
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Solar