Solar Increase
5 MW generation in Hartford, CT · In queue since February 2023 · Proposed COD June 2026
5 MW
Capacity
1
Components
Solar
3y 3m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Total Duration
3y 4m
Interconnection request submitted to ISO/RTO
ISO-NE is transitioning to cluster studies per FERC Order 2023.
Typical: 25–30 months (recent)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-06-15
The Solar Increase project is a proposed 5 MW solar generation project located in Hartford County, Connecticut. The project is listed in the ISO-NE interconnection queue as queue ID ISO-NE-1357, with an entry date of February 16, 2023, and a proposed commercial operation date of June 15, 2026. The interconnection agreement status is listed as "In Progress (unknown study)".
The project intends to interconnect at the point of interconnection (POI) of Gravel Pit Solar (QP 1030 + QP 1247), as an increase to QP 1030 and QP1247. The POI is the new Gravel Pit Solar substation at the new three-breaker ring bus on the 115 kV Connecticut Light & Power Company 1200 line between Barbour Hill and Windsor Locks.
Generated from interconnection queue and public data sources
State
CT
County
Hartford
Grid Region
ISO New England
Market
ISO/RTO Member
Developer
—
Utility
—
Entity
ISO-NE
Service Type
—
Point of Interconnection
To interconnect at the POI of Gravel Pit Solar (QP 1030 + QP 1247), as an increase to QP 1030 and QP1247, the POI is the new Gravel Pit Solar substation at the new three-breaker ring bus on the 115 kV Connecticut Light & Power Company 1200 line between Barbour Hill and Windsor Locks.
Data Source
LBNL + Live
- ISO / RTO
- ISO-NE
- Trading Hub
- .Z.CONNECTICUT
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.