Battery Storage
179.47 MW storage in Bristol, MA · In queue since June 2023 · Proposed COD September 2027
179.47 MW
Capacity
1
Components
Battery
2y 11m
In Queue
Feasibility Study
IA Status
COD target: 2027
Total Duration
4y 3m
Interconnection request submitted to ISO/RTO
ISO-NE is transitioning to cluster studies per FERC Order 2023.
Typical: 25–30 months (recent)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-09-30
The Battery Storage project is a proposed 179.47 MW battery storage development in Bristol County, Massachusetts. The project, located in the ISO-NE region, consists entirely of battery storage. It is listed in the ISO-NE interconnection queue as entry ISO-NE-1412, with a queue entry date of June 20, 2023, and a proposed commercial operation date of September 30, 2027.
The project's interconnection status is currently in the Feasibility Study phase. The point of interconnection is a direct tap into the Pottersville Substation in Somerset, MA. The project has appeared in recent news.
Generated from interconnection queue and public data sources
State
MA
County
Bristol
Grid Region
ISO New England
Market
ISO/RTO Member
Developer
—
Utility
—
Entity
ISO-NE
Service Type
—
Point of Interconnection
Direct tap into the Pottersville Substation in Somerset, MA
Data Source
LBNL + Live
- ISO / RTO
- ISO-NE
- Trading Hub
- .H.INTERNAL_HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- LD.HATHAWAY13.8
- POI Substation
- Pottersville Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.