Battery Storage
19.3 MW storage in Franklin, VT · In queue since March 2024 · Proposed COD July 2026
19.3 MW
Capacity
1
Components
Battery
2y 2m
In Queue
System Impact Study
IA Status
COD target: 2026
Total Duration
2y 4m
Interconnection request submitted to ISO/RTO
ISO-NE is transitioning to cluster studies per FERC Order 2023.
Typical: 25–30 months (recent)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-07-01
The Battery Storage project is a proposed 19.3 MW battery storage development in Franklin County, Vermont. The project is located within the ISO-NE region and interconnected via direct connection to the VELCO 115kV Highgate substation (44.943833, -73.058515).
The project, identified as queue ID ISO-NE-1502, entered the ISO-NE interconnection queue on March 28, 2024, with a proposed commercial operation date of July 1, 2026. Its interconnection status is currently in the System Impact Study phase. The project has appeared in recent news.
Generated from interconnection queue and public data sources
State
VT
County
Franklin
Grid Region
ISO New England
Market
ISO/RTO Member
Developer
—
Utility
—
Entity
ISO-NE
Service Type
—
Point of Interconnection
Direct connection to VELCO 115kV Highgate substation (44.943833, -73.058515)
Data Source
LBNL + Live
- ISO / RTO
- ISO-NE
- Trading Hub
- .Z.VERMONT
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- UN.HIGHGATE13.8SWC1
- POI Substation
- Highgate Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Battery Storage