Battery Storage
202.07 MW storage in Hampden, MA · In queue since May 2024 · Proposed COD January 2030
202.07 MW
Capacity
1
Components
Battery
2 years
In Queue
Feasibility Study
IA Status
COD target: 2030
Total Duration
5y 8m
Interconnection request submitted to ISO/RTO
ISO-NE is transitioning to cluster studies per FERC Order 2023.
Typical: 25–30 months (recent)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-01-24
The Battery Storage project is a proposed 202.07 MW battery storage development in Hampden County, Massachusetts. The project, located within the ISO-NE region, consists of a 202.07 MW battery energy storage system. It is listed in the ISO-NE interconnection queue as queue ID 1542, with an entry date of May 28, 2024.
The proposed commercial operation date for the Battery Storage project is January 24, 2030. Its interconnection status is currently in the Feasibility Study phase. The point of interconnection is the MA_WMECO Blandford 115kV substation. The project has appeared in recent news.
Generated from interconnection queue and public data sources
State
MA
County
Hampden
Grid Region
ISO New England
Market
ISO/RTO Member
Developer
—
Utility
—
Entity
ISO-NE
Service Type
—
Point of Interconnection
MA_WMECO Blandford 115kV substation
Data Source
LBNL + Live
- ISO / RTO
- ISO-NE
- Trading Hub
- .H.INTERNAL_HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.