Battery Storage
190 MW storage in Worcester, MA · In queue since May 2024 · Proposed COD January 2027
190 MW
Capacity
1
Components
Battery
2 years
In Queue
System Impact Study
IA Status
COD target: 2027
Total Duration
2y 8m
Interconnection request submitted to ISO/RTO
ISO-NE is transitioning to cluster studies per FERC Order 2023.
Typical: 25–30 months (recent)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-01-31
A proposed 190 MW battery storage project, known as Battery Storage (ISO-NE-1551), is under development in Worcester County, Massachusetts. The project, located within the ISO-NE region, consists entirely of battery storage. It entered the ISO-NE interconnection queue on May 31, 2024, with a proposed commercial operation date of January 31, 2027. The project's interconnection status is currently in the System Impact Study phase.
The Primary Point of Interconnection will be located on the project's property at coordinates 42°21'44.53"N, 72°2'22.57"W, tapping the 115-kV Line A127-4 (Barre-Paxton) approximately 6 km from Barre Substation, which is owned by MA_NGRID.
Generated from interconnection queue and public data sources
State
MA
County
Worcester
Grid Region
ISO New England
Market
ISO/RTO Member
Developer
—
Utility
—
Entity
ISO-NE
Service Type
—
Point of Interconnection
The Primary Point of Interconnection will be located on the IC_x0019_s property (Lat, long: 4221'44.53"N, 72 2'22.57"W) by tapping the 115-kV Line A127-4 (Barre-Paxton) at approx. 6km from Barre Substation owned by MA_NGRID.
Data Source
LBNL + Live
- ISO / RTO
- ISO-NE
- Trading Hub
- .H.INTERNAL_HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- LD.BARRE 13.8
- POI Substation
- Barre Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.