Battery Storage
214.157 MW storage in Essex, MA · In queue since June 2024 · Proposed COD January 2028
214.157 MW
Capacity
1
Components
Battery
1y 11m
In Queue
System Impact Study
IA Status
COD target: 2028
Total Duration
3y 7m
Interconnection request submitted to ISO/RTO
ISO-NE is transitioning to cluster studies per FERC Order 2023.
Typical: 25–30 months (recent)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-01-01
The Battery Storage project is a proposed 214.16 MW battery storage development in Essex County, Massachusetts. The project is located within the ISO-NE region and is listed in the ISO-NE interconnection queue as queue ID 1555, with an entry date of June 6, 2024. The proposed commercial operation date is January 1, 2028.
The project's interconnection status is currently in the System Impact Study phase. The point of interconnection (POI) is the 115KV Line Q-169 between Resco-Saugus Tap and Melrose #2 Tap, approximately 2.4 miles from Melrose #2 Tap and approximately 2.35 miles from Resco-Saugus Tap.
Generated from interconnection queue and public data sources
State
MA
County
Essex
Grid Region
ISO New England
Market
ISO/RTO Member
Developer
—
Utility
—
Entity
ISO-NE
Service Type
—
Point of Interconnection
115KV Line Q-169 between Resco-Saugus Tap and Melrose #2 Tap. Approximately 2.4 miles from Melrose #2 Tap and approximately 2.35 miles from Resco-Saugus Tap
Data Source
LBNL + Live
- ISO / RTO
- ISO-NE
- Trading Hub
- .H.INTERNAL_HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.