Battery Storage (ISO-NE-1567) — Project Summary

Queue ID
ISO-NE-1567
Capacity
514.799988 MW
Technology
Battery
Status
active
Location
Middlesex, MA
Region
ISO-NE
Developer
IA Status
System Impact Study

Battery Storage

ISO-NE-1567BetaActiveBatteryISO-NELBNL + Live

514.8 MW storage in Middlesex, MA · In queue since June 2024 · Proposed COD January 2027

514.8 MW

Capacity

1

Components

Battery

1y 11m

In Queue

System Impact Study

IA Status

COD target: 2027

Interconnection

Total Duration

2y 7m

Impact Study25%
Queue EntryJun 11, 2024

Interconnection request submitted to ISO/RTO

TCS StudyCurrent

ISO-NE is transitioning to cluster studies per FERC Order 2023.

Typical: 25–30 months (recent)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-01-31

About

The proposed Battery Storage project is a 514.8 MW battery storage development in Middlesex County, Massachusetts. The project, under queue ID ISO-NE-1567, is located within the ISO-NE region and was entered into the interconnection queue on June 11, 2024. The developer has proposed a commercial operation date of January 31, 2027.

The project's interconnection status is currently in the System Impact Study phase. The Primary Point of Interconnection will be a direct interconnection located on the property at coordinates 42°41'23.38"N, 71°26'20.43"W, tapping the 345-kV Line 326-2 (Sandy Pond-Lawrence Rd), owned by RI_NGRID, approximately 8.4 miles from the 345-kV Lawrence Rd Substation. The project has appeared in recent news.

Generated from interconnection queue and public data sources

Project Details

State

MA

County

Middlesex

Grid Region

ISO New England

Market

ISO/RTO Member

Developer

Utility

Entity

ISO-NE

Service Type

Point of Interconnection

The Primary Point of Interconnection will be a direct interconnection will be located on the IC_x0019_s property (Lat, long: 4241'23.38"N, 7126'20.43"W) by tapping the 345-kV Line 326-2 (Sandy Pond-Lawrence Rd), owned by RI_NGRID, at approx. 8.4 miles from the 345-kV Lawerence Rd Substation.

Data Source

LBNL + Live

Market Context
Approximate
ISO / RTO
ISO-NE
Trading Hub
.H.INTERNAL_HUB
Hub Confidence
MEDIUM

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.