Park City Offshore Wind
791 MW generation in MA · In queue since December 2017 · Proposed COD December 2029
791 MW
Capacity
1
Components
Offshore Wind
8y 5m
In Queue
IA Executed
IA Status
COD target: 2029
Total Duration
12 years
Interconnection request submitted to ISO/RTO
ISO-NE is transitioning to cluster studies per FERC Order 2023.
Typical: 25–30 months (recent)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 36–60 months
Proposed COD: 2029-12-31
Park City Offshore Wind is a proposed 791 MW offshore wind generation project located in Massachusetts. The development project, sponsored by ISO-NE, is currently active in the ISO-NE interconnection queue as queue ID ISO-NE-700. The project entered the queue on December 15, 2017, and has a proposed commercial operation date of December 31, 2029. The interconnection agreement has been executed. The point of interconnection is the Eversource 345 kV West Barnstable Substation.
The Park City Offshore Wind project has been the subject of recent news coverage, with 244 articles appearing in the press. These articles primarily focus on regulatory matters, with some coverage of industry, development, and deals related to the project.
Generated from interconnection queue and public data sources
State
MA
County
—
Grid Region
ISO New England
Market
ISO/RTO Member
Developer
—
Utility
ISO-NE
Entity
ISO-NE
Service Type
—
Point of Interconnection
Eversource 345 kV West Barnstable Substation
Data Source
LBNL + Live
- ISO / RTO
- ISO-NE
- Trading Hub
- .H.INTERNAL_HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- LD.OAK_ST 23
- POI Substation
- West Barnstable Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-14