Revoultion Offshore wind (ISO-NE-781) — Project Summary

Queue ID
ISO-NE-781
Capacity
704 MW
Technology
Offshore Wind
Status
active
Location
RI
Region
ISO-NE
Developer
IA Status
IA Executed

Revoultion Offshore wind

ISO-NE-781BetaActiveOffshore WindISO-NELBNL + Live

704 MW generation in RI · In queue since September 2018 · Proposed COD September 2025

704 MW

Capacity

1

Components

Offshore Wind

7y 8m

In Queue

IA Executed

IA Status

COD target: 2025

Status
as of 2 years ago
Latest milestoneoffshore construction commenced · 2024Power Technology · 2024-05-16
Expected COD2025Power Technology · 2024-05-16
Interconnection

Total Duration

7 years

Schedule

8 months past proposed COD

Construction75%
Queue EntrySep 13, 2018

Interconnection request submitted to ISO/RTO

TCS Study

ISO-NE is transitioning to cluster studies per FERC Order 2023.

Typical: 25–30 months (recent)

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 36–60 months

Commercial Operation

Proposed COD: 2025-09-07

About

The Revolution Offshore Wind project is a proposed 704 MW offshore wind generation facility in Washington County, Rhode Island. The project is located within the ISO-NE service area and is listed in the ISO-NE interconnection queue as queue ID 781, with an entry date of September 13, 2018. The proposed commercial operation date is September 7, 2025, and the Interconnection Agreement has been executed.

The Revolution Offshore Wind project has been the subject of recent news coverage, with 53 articles appearing in the news. These articles primarily focus on development aspects of the project.

Generated from interconnection queue and public data sources

Project Details

State

RI

County

Grid Region

ISO New England

Market

ISO/RTO Member

Developer

Utility

ISO-NE

Entity

ISO-NE

Service Type

Point of Interconnection

NG 115 kV Davisville substation, Washington County

Data Source

LBNL + Live

DeveloperOrsted±Power Technology · 2024-05-16
EPC contractorNexansOffshore Engineer Magazine · 2022-03-10
ApplicantØrstedCleanTechnica · 2025-08-25
AgencyBOEM±RTO Insider · 2025-09-22
RulingOrderRTO Insider · 2025-09-22
TransactionProject financingOffshore Energy · 2022-10-06
OfftakerBP and EquinorOffshore Energy · 2022-10-06
Market Context
Approximate
ISO / RTO
ISO-NE
Trading Hub
.Z.RHODEISLAND
Hub Confidence
HIGH
Nearest Node (Estimated)
LD.WASHNGTN34.5
POI Substation
Washington County Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

News & Articles (9)Beta

Last updated 2026-03-31

View all 9 articles

No ask pi reports yet for this entity.

ask pi about Revoultion Offshore wind