Three Rivers Solar (ISO-NE-833) — Project Summary

Queue ID
ISO-NE-833
Capacity
100 MW
Technology
Solar
Status
active
Location
Hancock, ME
Region
ISO-NE
Developer
IA Status
IA Executed

Three Rivers Solar

ISO-NE-833BetaActiveSolarISO-NELBNL + Live

100 MW generation in Hancock, ME · In queue since January 2019 · Proposed COD December 2026

100 MW

Capacity

1

Components

Solar

7y 4m

In Queue

IA Executed

IA Status

COD target: 2026

Interconnection

Total Duration

7y 11m

Construction75%
Queue EntryJan 9, 2019

Interconnection request submitted to ISO/RTO

TCS Study

ISO-NE is transitioning to cluster studies per FERC Order 2023.

Typical: 25–30 months (recent)

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2026-12-31

About

Three Rivers Solar is a proposed 100 MW solar generation project located in Hancock County, Maine. The project is listed in the ISO-NE interconnection queue as queue ID 833, with an entry date of January 9, 2019, and a proposed commercial operation date of December 31, 2026. The interconnection agreement for the project has been executed.

The proposed project is linked to the existing Three Rivers Solar Power, LLC operating plant (EIA ID 63386). It has been the subject of recent news coverage related to regulatory matters.

Generated from interconnection queue and public data sources

Project Details

State

ME

County

Hancock

Grid Region

ISO New England

Market

ISO/RTO Member

Developer

Utility

ISO-NE

Entity

ISO-NE

Service Type

Point of Interconnection

New 115 kV breaker Ring bus, tapping 115 kV Line 93 (Emera Maine) between Bull Hill & Deblois

Data Source

LBNL + Live

Market Context
Approximate
ISO / RTO
ISO-NE
Trading Hub
.Z.MAINE
Hub Confidence
HIGH
Nearest Node (Estimated)
Pending
POI Substation
Bull Hill Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.