West Baldwin Solar
17.1 MW generation in Cumberland, ME · In queue since October 2019 · Proposed COD September 2029
17.1 MW
Capacity
1
Components
Solar
6y 7m
In Queue
IA Executed
IA Status
COD target: 2029
Total Duration
9y 11m
Interconnection request submitted to ISO/RTO
ISO-NE is transitioning to cluster studies per FERC Order 2023.
Typical: 25–30 months (recent)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2029-09-30
West Baldwin Solar is a proposed 17.1 MW solar generation project located in Cumberland County, Maine. The project is in the ISO-NE interconnection queue as entry ISO-NE-935, with a queue entry date of October 30, 2019, and a proposed commercial operation date of September 30, 2029. The interconnection agreement (IA) has been executed.
The proposed project is linked to the existing West Baldwin Solar Station operating plant (EIA ID 65371). The point of interconnection is the CMP 34.5 kv Line, Section 91. The project has appeared in recent news.
Generated from interconnection queue and public data sources
State
ME
County
Cumberland
Grid Region
ISO New England
Market
ISO/RTO Member
Developer
—
Utility
ISO-NE
Entity
ISO-NE
Service Type
—
Point of Interconnection
CMP 34.5 kv Line, Section 91
Data Source
LBNL + Live
- ISO / RTO
- ISO-NE
- Trading Hub
- .Z.MAINE
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- UN.W_BUXTON34.5HIRM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about West Baldwin Solar