JEA-JEA-Q007-PV
50 MW generation in Duval, FL · In queue since December 2017 · Proposed COD December 2020
50 MW
Capacity
1
Components
Solar
8y 5m
In Queue
IA Executed
IA Status
COD target: 2020
Total Duration
3 years
Schedule
65 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2020-12-31
The proposed JEA-JEA-Q007-PV project is a 50 MW solar generation project located in Duval County, Florida. The project is being developed within the Jacksonville Electric Authority (JEA) utility territory.
This development project is in the JEA interconnection queue as of December 21, 2017, with a proposed commercial operation date of December 31, 2020. The project's interconnection agreement (IA) has been executed.
Generated from interconnection queue and public data sources
State
FL
County
Duval
Grid Region
Southeast
Market
—
Developer
—
Utility
Jacksonville Electric Authority
Entity
JEA
Service Type
—
Point of Interconnection
Dinsmore Sub
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- FRCC
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project JEA-JEA-Q007-PV