JEA-JEA-Q008
645 MW generation in Duval, FL · In queue since February 2018 · Proposed COD May 2023
645 MW
Capacity
1
Components
Gas
8y 3m
In Queue
Feasibility Study
IA Status
COD target: 2023
Total Duration
5y 3m
Schedule
37 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-05-01
JEA-JEA-Q008 is a proposed 645 MW gas-fired generation project located in Duval County, Florida. The project is being developed by Jacksonville Electric Authority (JEA). It consists of a single 645 MW gas component.
The project is listed in the Jacksonville Electric Authority (JEA) interconnection queue with an entry date of February 22, 2018. The proposed commercial operation date is May 1, 2023. The interconnection status is currently in the Feasibility Study phase, and the point of interconnection is the Greenland Energy Center.
Generated from interconnection queue and public data sources
State
FL
County
Duval
Grid Region
Southeast
Market
—
Developer
—
Utility
Jacksonville Electric Authority
Entity
JEA
Service Type
—
Point of Interconnection
Greenland Energy Center
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- FRCC
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project JEA-JEA-Q008