JEA-JEA-Q011
74.9 MW hybrid in Duval, FL · In queue since May 2024 · Proposed COD December 2026
74.9 MW
Capacity
1
Components
Solar
2 years
In Queue
Feasibility Study
IA Status
COD target: 2026
Total Duration
2y 7m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-12-31
The proposed JEA-JEA-Q011 project is a 74.9 MW hybrid Solar+Battery development project located in Duval County, Florida. The project, consisting of 74.9 MW of solar capacity, is in the Jacksonville Electric Authority (JEA) interconnection queue with an entry date of May 9, 2024. The proposed commercial operation date is December 31, 2026.
The project's interconnection status is currently in the Feasibility Study phase. The point of interconnection is the Caldwell substation. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
FL
County
Duval
Grid Region
Southeast
Market
—
Developer
—
Utility
Jacksonville Electric Authority
Entity
JEA
Service Type
—
Point of Interconnection
Caldwell
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- FRCC
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project JEA-JEA-Q011