Project LADWP-Q08 — Project Summary

Queue ID
LADWP-Q08
Capacity
150 MW
Technology
Solar
Status
active
Location
Clark, NV
Region
West
Developer
IA Status
Feasibility Study

LADWP-Q08

LADWP-Q08BetaActiveSolarLADWPLBNL

150 MW generation in Clark, NV · In queue since March 2009 · Proposed COD August 2014

150 MW

Capacity

1

Components

Solar

17y 2m

In Queue

Feasibility Study

IA Status

COD target: 2014

Interconnection

Total Duration

5y 5m

Schedule

143 months past proposed COD

Feasibility Study13%
Queue EntryMar 26, 2009

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2014-08-01

About

LADWP-Q08 is a proposed solar generation project with a total capacity of 150 MW, located in Clark County, Nevada. The project is listed in the Los Angeles Department of Water and Power interconnection queue, with an entry date of March 26, 2009. The proposed commercial operation date is August 1, 2014.

The interconnection status of the project is currently in the Feasibility Study phase. The point of interconnection is the McCullough 230kV Substation.

Generated from interconnection queue and public data sources

Project Details

State

NV

County

Clark

Grid Region

Mountain West

Market

Developer

Utility

Los Angeles Department of Water and Power

Entity

LADWP

Service Type

Point of Interconnection

McCullough 230kV Substation

Data Source

LBNL

Market Context
Approximate
ISO / RTO
MOUNTAIN_WEST
Trading Hub
PALOVERDE
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.