LADWP-Q101
1,000 MW hybrid in Los Angeles, CA · In queue since April 2023 · Proposed COD November 2030
1,000 MW
Capacity
1
Components
Wind
3y 1m
In Queue
In Progress (unknown study)
IA Status
COD target: 2030
Total Duration
7y 7m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-11-30
LADWP-Q101 is a proposed 1000 MW hybrid wind and battery project located in Los Angeles County, California. The project consists of 1000 MW of wind generation capacity. It is being developed by the Los Angeles Department of Water and Power (LADWP) and is currently active in the LADWP interconnection queue, with a queue entry date of April 14, 2023. The proposed commercial operation date is November 30, 2030.
The interconnection agreement (IA) status for LADWP-Q101 is listed as "In Progress (unknown study)". The point of interconnection (POI) is the Wilmington 138kV substation. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
CA
County
Los Angeles
Grid Region
Mountain West
Market
—
Developer
—
Utility
Los Angeles Department of Water and Power
Entity
LADWP
Service Type
—
Point of Interconnection
Wilmington 138kV
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project LADWP-Q101