LADWP-Q102
930 MW hybrid in Mohave, AZ · In queue since April 2023 · Proposed COD November 2027
930 MW
Capacity
1
Components
Solar
3y 1m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Total Duration
4y 7m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-11-30
LADWP-Q102 is a proposed 930 MW hybrid solar and battery project located in Mohave County, Arizona. The Los Angeles Department of Water and Power (LADWP) is the listed developer. The project consists of 930 MW of solar capacity.
The project is listed in the LADWP interconnection queue with an entry date of April 28, 2023, and a proposed commercial operation date of November 30, 2027. Its interconnection agreement status is listed as "In Progress (unknown study)". The point of interconnection is Marketplace 500kV.
Generated from interconnection queue and public data sources
State
AZ
County
Mohave
Grid Region
Mountain West
Market
—
Developer
—
Utility
Los Angeles Department of Water and Power
Entity
LADWP
Service Type
—
Point of Interconnection
Marketplace 500kV
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.