LADWP-Q109
100 MW storage in Los Angeles, CA · In queue since June 2024 · Proposed COD July 2027
100 MW
Capacity
1
Components
Battery
1y 11m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Total Duration
3y 1m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-07-01
The LADWP-Q109 development project is a proposed 100 MW battery storage project located in Los Angeles County, California. The project, under development by the Los Angeles Department of Water and Power (LADWP), entered the LADWP interconnection queue on June 19, 2024. The proposed commercial operation date is July 1, 2027.
The interconnection status is listed as "In Progress (unknown study)". The point of interconnection (POI) is the River 230kV Switching Station. The project consists of 100 MW of battery storage capacity.
Generated from interconnection queue and public data sources
State
CA
County
Los Angeles
Grid Region
Mountain West
Market
—
Developer
—
Utility
Los Angeles Department of Water and Power
Entity
LADWP
Service Type
—
Point of Interconnection
River 230kV Switching Station
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.