LADWP-Q111
500 MW hybrid in Clark, NV · In queue since June 2024 · Proposed COD June 2026
500 MW
Capacity
2
Components
Solar + Battery
1y 11m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Total Duration
2 years
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-06-30
LADWP-Q111 is a proposed 500 MW hybrid solar and battery project located in Clark County, Nevada. The project, developed by the Los Angeles Department of Water and Power (LADWP), consists of 250 MW of solar generation coupled with 250 MW of battery energy storage. It is actively listed in the LADWP interconnection queue as of June 27, 2024, with a proposed commercial operation date of June 30, 2026.
The interconnection agreement for LADWP-Q111 is currently in progress, with the specific study being conducted not specified. The point of interconnection is the Marketplace 500kV Switching Station. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
NV
County
Clark
Grid Region
Mountain West
Market
—
Developer
—
Utility
Los Angeles Department of Water and Power
Entity
LADWP
Service Type
—
Point of Interconnection
Marketplace 500kV Switching Station
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.