LADWP-Q37
200 MW hybrid in Clark, NV · In queue since November 2012 · Proposed COD April 2015
200 MW
Capacity
2
Components
Solar + Battery
13y 6m
In Queue
Facility Study
IA Status
COD target: 2015
Total Duration
2y 5m
Schedule
134 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2015-04-30
LADWP-Q37 is a proposed 200 MW hybrid solar and battery project located in Clark County, Nevada. The project, developed by the Los Angeles Department of Water and Power (LADWP), consists of 100 MW of solar generation and 100 MW of battery energy storage. It is interconnected to the Marketplace Substation.
The project is listed in the LADWP interconnection queue with an entry date of November 28, 2012. The proposed commercial operation date is April 30, 2015. Its interconnection status is currently in the Facility Study phase.
Generated from interconnection queue and public data sources
State
NV
County
Clark
Grid Region
Mountain West
Market
—
Developer
—
Utility
Los Angeles Department of Water and Power
Entity
LADWP
Service Type
—
Point of Interconnection
Marketplace Substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project LADWP-Q37