LADWP-Q52
518 MW hybrid in Millard, UT · In queue since January 2016 · Proposed COD December 2018
518 MW
Capacity
2
Components
Solar + Battery
10y 4m
In Queue
Operational
IA Status
COD target: 2018
Total Duration
2y 11m
Schedule
89 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2018-12-31
LADWP-Q52 is a proposed 518 MW hybrid solar and battery project located in Millard County, Utah. The developer is Intermountain Power Agency, and the Los Angeles Department of Water and Power (LADWP) is the interconnecting utility. The project consists of a 324 MW solar array and a 194 MW battery energy storage system.
The project is in the LADWP interconnection queue, with an original queue entry date of January 14, 2016, and a proposed commercial operation date of December 31, 2018. The interconnection agreement status is listed as operational.
Generated from interconnection queue and public data sources
State
UT
County
Millard
Grid Region
Mountain West
Market
—
Developer
Intermountain Power Agency
Utility
Los Angeles Department of Water and Power
Entity
LADWP
Service Type
—
Point of Interconnection
IPP 345kV Switchyard
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.