LADWP-Q53
570 MW hybrid in Millard, UT · In queue since July 2016 · Proposed COD June 2019
570 MW
Capacity
2
Components
Solar + Battery
9y 10m
In Queue
IA Pending
IA Status
COD target: 2019
Total Duration
2y 11m
Schedule
83 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2019-06-30
The LADWP-Q53 development project is a proposed 570 MW hybrid solar and battery energy storage project located in Millard County, Utah. The project, being developed by Intermountain Power Agency, consists of 285 MW of solar generation and 285 MW of battery storage. It is interconnected to the Los Angeles Department of Water and Power (LADWP) system at the IPP 345kV Switchyard.
The project is currently listed as active in the LADWP interconnection queue, with an original queue entry date of July 28, 2016. The proposed commercial operation date is June 30, 2019, and the Interconnection Agreement (IA) is currently pending.
Generated from interconnection queue and public data sources
State
UT
County
Millard
Grid Region
Mountain West
Market
—
Developer
Intermountain Power Agency
Utility
Los Angeles Department of Water and Power
Entity
LADWP
Service Type
—
Point of Interconnection
IPP 345kV Switchyard
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.