Project LADWP-Q53 — Project Summary

Queue ID
LADWP-Q53
Capacity
570 MW
Technology
Solar+Battery
Status
active
Location
Millard, UT
Region
West
Developer
Intermountain Power Agency
IA Status
IA Pending

LADWP-Q53

LADWP-Q53BetaActiveSolarBatteryLADWPLBNL

570 MW hybrid in Millard, UT · In queue since July 2016 · Proposed COD June 2019

570 MW

Capacity

2

Components

Solar + Battery

9y 10m

In Queue

IA Pending

IA Status

COD target: 2019

Interconnection

Total Duration

2y 11m

Schedule

83 months past proposed COD

In Study38%
Queue EntryJul 28, 2016

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2019-06-30

Technology
Solar285 MW · 50%
Battery285 MW · 50%
About

The LADWP-Q53 development project is a proposed 570 MW hybrid solar and battery energy storage project located in Millard County, Utah. The project, being developed by Intermountain Power Agency, consists of 285 MW of solar generation and 285 MW of battery storage. It is interconnected to the Los Angeles Department of Water and Power (LADWP) system at the IPP 345kV Switchyard.

The project is currently listed as active in the LADWP interconnection queue, with an original queue entry date of July 28, 2016. The proposed commercial operation date is June 30, 2019, and the Interconnection Agreement (IA) is currently pending.

Generated from interconnection queue and public data sources

Project Details

State

UT

County

Millard

Grid Region

Mountain West

Market

Developer

Intermountain Power Agency

Utility

Los Angeles Department of Water and Power

Entity

LADWP

Service Type

Point of Interconnection

IPP 345kV Switchyard

Data Source

LBNL

Market Context
Approximate
ISO / RTO
MOUNTAIN_WEST
Trading Hub
FOURCORNERS
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.