LADWP-Q62
75 MW storage in Los Angeles, CA · In queue since October 2017 · Proposed COD June 2020
75 MW
Capacity
1
Components
Battery
8y 7m
In Queue
System Impact Study
IA Status
COD target: 2020
Total Duration
2y 8m
Schedule
72 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2020-06-01
The LADWP-Q62 development project is a proposed 75 MW battery storage project located in Los Angeles County, California. The project is listed in the Los Angeles Department of Water and Power (LADWP) interconnection queue, with an entry date of October 3, 2017. The proposed commercial operation date is June 1, 2020.
The project's interconnection status is currently in the System Impact Study phase. The point of interconnection is the 138kV Bus Station C in Wilmington.
Generated from interconnection queue and public data sources
State
CA
County
Los Angeles
Grid Region
Mountain West
Market
—
Developer
—
Utility
Los Angeles Department of Water and Power
Entity
LADWP
Service Type
—
Point of Interconnection
138kV Bus Station C Wilmington
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project LADWP-Q62