LADWP-Q69
300 MW hybrid in San Bernardino, CA · In queue since April 2019 · Proposed COD September 2022
300 MW
Capacity
2
Components
Solar + Battery
7y 1m
In Queue
Facility Study
IA Status
COD target: 2022
Total Duration
3y 5m
Schedule
44 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2022-09-15
LADWP-Q69 is a proposed 300 MW hybrid solar and battery project located in San Bernardino County, California. The project, developed by the Los Angeles Department of Water and Power (LADWP), consists of a 200 MW solar component and a 100 MW battery energy storage system. It is currently active in the LADWP interconnection queue, with an entry date of April 15, 2019, and a proposed commercial operation date of September 15, 2022. The project's interconnection status is currently in the Facility Study phase, and it intends to connect to the Mead-Victorville 287kV Line.
The proposed project is located in the Western region of the United States. It is listed in the interconnection queue under queue ID LADWP-Q69. Recent news coverage has discussed the development of this project.
Generated from interconnection queue and public data sources
State
CA
County
San Bernardino
Grid Region
Mountain West
Market
—
Developer
—
Utility
Los Angeles Department of Water and Power
Entity
LADWP
Service Type
—
Point of Interconnection
Mead-Victorville 287kV Line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.