LADWP-Q70
500 MW hybrid in Kern, CA · In queue since May 2019 · Proposed COD December 2022
500 MW
Capacity
2
Components
Solar + Battery
7 years
In Queue
Facility Study
IA Status
COD target: 2022
Total Duration
3y 7m
Schedule
42 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2022-12-01
LADWP-Q70 is a proposed 500 MW hybrid Solar+Battery project located in Kern County, California. The development project, which appeared in the Los Angeles Department of Water and Power (LADWP) interconnection queue on May 2, 2019, consists of 250 MW of solar generation and 250 MW of battery energy storage. The proposed commercial operation date is December 1, 2022.
The project's interconnection status is currently in the Facility Study phase. The point of interconnection is the Rosamond 230kV Switching Station.
Generated from interconnection queue and public data sources
State
CA
County
Kern
Grid Region
Mountain West
Market
—
Developer
—
Utility
Los Angeles Department of Water and Power
Entity
LADWP
Service Type
—
Point of Interconnection
Rosamond 230kV Switching Station
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.