LADWP-Q81
200 MW storage in Los Angeles, CA · In queue since May 2021 · Proposed COD August 2024
200 MW
Capacity
1
Components
Battery
5 years
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Total Duration
3y 3m
Schedule
21 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-08-01
The LADWP-Q81 project is a proposed 200 MW battery storage project located in Los Angeles County, California. The project is being developed by the Los Angeles Department of Water and Power (LADWP). It consists of a 200 MW battery energy storage system.
The project is currently in the LADWP interconnection queue with an entry date of May 11, 2021. The proposed commercial operation date is August 1, 2024. The interconnection agreement status is listed as "In Progress (unknown study)". The point of interconnection is the Northridge 230 kV Substation.
Generated from interconnection queue and public data sources
State
CA
County
Los Angeles
Grid Region
Mountain West
Market
—
Developer
—
Utility
Los Angeles Department of Water and Power
Entity
LADWP
Service Type
—
Point of Interconnection
Northridge 230 kV Substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project LADWP-Q81