LADWP-Q90
800 MW hybrid in Millard, UT · In queue since April 2022 · Proposed COD March 2027
800 MW
Capacity
2
Components
Solar + Battery
4y 1m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Total Duration
4y 11m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-03-27
LADWP-Q90 is a proposed 800 MW hybrid solar and battery project located in Millard County, Utah. The development project, proposed by Intermountain Power Agency, consists of 400 MW of solar generation paired with 400 MW of battery storage. It is interconnected to the Los Angeles Department of Water and Power (LADWP) system at the IPP-Mona 345kV Line point of interconnection.
The project is currently active in the LADWP interconnection queue, with an entry date of April 1, 2022. The proposed commercial operation date is March 27, 2027. The interconnection agreement is currently in progress, with the specific study status unknown.
Generated from interconnection queue and public data sources
State
UT
County
Millard
Grid Region
Mountain West
Market
—
Developer
Intermountain Power Agency
Utility
Los Angeles Department of Water and Power
Entity
LADWP
Service Type
—
Point of Interconnection
IPP-Mona 345kV Line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.