LADWP-Q92
1,650 MW hybrid in San Bernardino, CA · In queue since June 2022 · Proposed COD December 2025
1,650 MW
Capacity
1
Components
Solar
3y 11m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
3y 6m
Schedule
4 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-12-31
LADWP-Q92 is a proposed 1650 MW hybrid solar and battery project located in San Bernardino County, California. The project, being developed by LADWP, consists of 1650 MW of solar capacity. It is currently active in the Los Angeles Department of Water and Power interconnection queue, with an entry date of June 20, 2022, and a proposed commercial operation date of December 31, 2025. The interconnection agreement status is listed as "In Progress (unknown study)". The point of interconnection is the Adelanto 500 KV Switchyard.
Generated from interconnection queue and public data sources
State
CA
County
San Bernardino
Grid Region
Mountain West
Market
—
Developer
—
Utility
Los Angeles Department of Water and Power
Entity
LADWP
Service Type
—
Point of Interconnection
Adelanto 500 KV Switchyard
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.