LADWP-Q94
700 MW hybrid in Millard, UT · In queue since December 2022 · Proposed COD March 2026
700 MW
Capacity
2
Components
Solar + Battery
3y 5m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Total Duration
3y 3m
Schedule
1 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-03-31
LADWP-Q94 is a proposed 700 MW hybrid solar and battery project located in Millard County, Utah. The developer is Intermountain Power Agency, and the Los Angeles Department of Water and Power (LADWP) is the interconnecting utility. The project consists of 400 MW of solar generation and 300 MW of battery energy storage.
The project is in the LADWP interconnection queue as of December 15, 2022, with a proposed commercial operation date of March 31, 2026. The interconnection agreement status is listed as "In Progress (unknown study)". The point of interconnection is the IPP 345kV Switchyard.
Generated from interconnection queue and public data sources
State
UT
County
Millard
Grid Region
Mountain West
Market
—
Developer
Intermountain Power Agency
Utility
Los Angeles Department of Water and Power
Entity
LADWP
Service Type
—
Point of Interconnection
IPP 345kV Switchyard
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.