LADWP-Q97
1,000 MW hybrid in Los Angeles, CA · In queue since March 2023 · Proposed COD November 2030
1,000 MW
Capacity
1
Components
Solar
3y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2030
Total Duration
7y 8m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-11-30
LADWP-Q97 is a proposed 1000 MW hybrid Solar+Battery project located in Los Angeles County, California. The project, being developed by LADWP, consists of 1000 MW of solar capacity. It is currently active in the Los Angeles Department of Water and Power interconnection queue, with a queue entry date of March 2, 2023, and a proposed commercial operation date of November 30, 2030. The interconnection agreement status is listed as "In Progress (unknown study)". The point of interconnection is the Haynes 230kV Switchyard.
Generated from interconnection queue and public data sources
State
CA
County
Los Angeles
Grid Region
Mountain West
Market
—
Developer
—
Utility
Los Angeles Department of Water and Power
Entity
LADWP
Service Type
—
Point of Interconnection
Haynes 230kV Switchyard
Data Source
LBNL