LADWP-Q99
800 MW hybrid in White Pine, NV · In queue since February 2023 · Proposed COD February 2029
800 MW
Capacity
1
Components
Solar
3y 3m
In Queue
In Progress (unknown study)
IA Status
COD target: 2029
Total Duration
6 years
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-02-15
LADWP-Q99 is a proposed 800 MW hybrid Solar+Battery project located in White Pine County, Nevada. The development project, which also includes Wind, is being proposed by Intermountain Power Agency and is under the Los Angeles Department of Water and Power (LADWP) utility. The project consists of 800 MW of solar capacity.
The project is currently active in the LADWP interconnection queue, with an entry date of February 28, 2023, and a proposed commercial operation date of February 15, 2029. Its interconnection agreement status is listed as "In Progress (unknown study)". The point of interconnection is the IPP-Gonder 230kV Line. The project has been mentioned in recent news coverage.
Generated from interconnection queue and public data sources
State
NV
County
White Pine
Grid Region
Mountain West
Market
—
Developer
Intermountain Power Agency
Utility
Los Angeles Department of Water and Power
Entity
LADWP
Service Type
—
Point of Interconnection
IPP-Gonder 230kV Line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-04-09