LGE-KU-LGE-GIS-2010-001
690 MW generation in Jefferson, KY · In queue since April 2010 · Proposed COD March 2015
690 MW
Capacity
1
Components
Gas
16y 1m
In Queue
IA Executed
IA Status
COD target: 2015
Total Duration
4y 11m
Schedule
136 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 24–48 months
Proposed COD: 2015-03-01
The proposed project LGE-KU-LGE-GIS-2010-001 is a 690 MW gas-fired generation project located in Jefferson County, Kentucky. The developer is Louisville Gas & Electric and Kentucky Utilities Energy (LGE-KU). It consists of 690 MW of gas-fired capacity.
The project is in the Louisville Gas & Electric and Kentucky Utilities Energy (LGE-KU) interconnection queue, with an entry date of April 7, 2010. The proposed commercial operation date is March 1, 2015, and the Interconnection Agreement (IA) has been executed. The point of interconnection (POI) is the Cane Run Switching Station 138 kV.
Generated from interconnection queue and public data sources
State
KY
County
Jefferson
Grid Region
Southeast
Market
—
Developer
—
Utility
Louisville Gas & Electric and Kentucky Utilities Energy
Entity
LGE-KU
Service Type
—
Point of Interconnection
Cane Run Switching Station 138 kV
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- TVA
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project LGE-KU-LGE-GIS-2010-001