LGE-KU-LGE-GIS-2016-001
8.5 MW generation in Clark, KY · In queue since March 2016 · Proposed COD April 2017
8.5 MW
Capacity
1
Components
Solar
10y 2m
In Queue
IA Executed
IA Status
COD target: 2017
Total Duration
1y 1m
Schedule
111 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2017-04-01
The proposed project LGE-KU-LGE-GIS-2016-001 is an 8.5 MW solar generation project located in Clark County, Kentucky. The developer is Louisville Gas & Electric and Kentucky Utilities Energy (LGE-KU). It consists of a single 8.5 MW solar component.
The project is in the Louisville Gas & Electric and Kentucky Utilities Energy (LGE-KU) interconnection queue, with an entry date of March 21, 2016. The proposed commercial operation date is April 1, 2017, and the Interconnection Agreement (IA) has been executed. The point of interconnection (POI) is the HQ Office 69 kV substation.
Generated from interconnection queue and public data sources
State
KY
County
Clark
Grid Region
Southeast
Market
—
Developer
—
Utility
Louisville Gas & Electric and Kentucky Utilities Energy
Entity
LGE-KU
Service Type
—
Point of Interconnection
HQ Office 69 kV
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- TVA
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project LGE-KU-LGE-GIS-2016-001