LGE-KU-LGE-GIS-2019-003
121 MW generation in Meade, KY · In queue since February 2019 · Proposed COD December 2022
121 MW
Capacity
1
Components
Solar
7y 3m
In Queue
Suspended
IA Status
COD target: 2022
Total Duration
3y 10m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2022-12-01
The proposed LGE-KU-LGE-GIS-2019-003 project is a 121 MW solar generation facility located in Meade County, Kentucky. The project is being developed by Louisville Gas & Electric and Kentucky Utilities Energy (LGE-KU). It is interconnected within the LGE-KU queue, having entered the queue on February 7, 2019, with a proposed commercial operation date of December 1, 2022.
The interconnection agreement (IA) status for the project is currently listed as suspended. The point of interconnection (POI) is the Cloverport _x0013_ Tiptop 138 kV line.
Generated from interconnection queue and public data sources
State
KY
County
Meade
Grid Region
Southeast
Market
—
Developer
—
Utility
Louisville Gas & Electric and Kentucky Utilities Energy
Entity
LGE-KU
Service Type
—
Point of Interconnection
Cloverport _x0013_ Tiptop 138 kV line
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- TVA
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.